1995The first rotary kiln equipment of Dongao plant was improved, and clinker annual production capacity was increased to 1.2 million tons. At this point, two cement rotary kiln equipments in the Companys Dongao plant had clinker annual production capacity was 2 million tons; Dongao plant and Puxin plant had a total grinding production capacity of cement was 3 million tons.
Taichung storage & transportation station add a cement silo to improve additional cement delivery capacity to the Central Taiwan.
Phase 1 expansion construction of Horen mining began, which was used to reinforce quality of developed mining source.
Puxin Plant researched and developed slag powder product and promote to customers.
Established Luckyship Navigation S.A.
Established Luckipar Professional Basketball Co., Ltd